CONSTRUCTION PHASES

Phase 1 – Preparation of construction site

Phase 1 – Preparation of construction siteTo be able to begin work on the tunnel, the complete area was prepared for construction. The area was secured, flattened, and measured. Temporary entrances and exits for construction vehicles were created.

Phase 2 – Installation of construction containers

Phase 3 – Relocation of traffic and cables

Phase 4 – Creating the sealing walls

Phase 5 – Excavation work in building dock

Phase 6 – Construction of tunnel elements

Phase 7 – Dredging of the tunnel section

Phase 8 – Floating of tunnel elements

Phase 9 – Sinking and positioning of tunnel elements

Phase 10 – Construction of the toll station

Phase 11 – Opening of the project on 12th September 2003